CFD42UBF24 series
Cold Front™ Planning Guide
Use liquid cooling to cut power and cooling costs
in your data center by 50% or more!
Use this guide to plan your Cold Front Heat-Transfer Door
and Transiiton Frame application.
Order toll-free in the U.S.: Call 877-877-BBOX (outside U.S. call 724-746-5500)
FREE technical support 24 hours a day, 7 days a week: Call 724-746-5500 or fax 724-746-0746
Mailing address: Black Box Corporation, 1000 Park Drive, Lawrence, PA 15055-1018
Customer
Support
Information
Cold Front Planning Guide
5. The transition frame weighs no more than 40 lb. (18 kg).
2.1.3 Connections and Piping
1. Supply and return connections on the HTD are brass ¾" or 1" ID quick-release couplings conforming to ISO 7241-1 Series B.
The female socket is used for supply water connection, and the male nipple is used for return water connection.
2. Bottom or top entry for the supply/return connection is available.
3. Supply/return headers on bottom-fed models have Schrader® valves for manual air bleeding.
4. Drain valve is on bottom of the HTD to allow the coil to drain completely.
5. Piping is copper, bent to minimize joints; any joints should be brazed.
2.1.4 Heat Exchanger Coil
1. Coil is constructed of copper tube and aluminum fin, 2 rows deep, 12 FPI.
2. Heat transferred by coil divided by initial temperature difference is no less than 440 W/°C at 2548 m ⁄
3 H
(1500 CFM) and
30 L/min (8 GPM) water flow.
3. Coil will be designed to minimize air-side and water-side pressure drops.
4. Maximum air-side pressure drop will not exceed 27 Pa (0.11 in H20) at 4077 m ⁄
sheets.
3 H
(2400 CFM) including coil and perforated
5. Maximum liquid-side pressure drop will be 53 kPa (7.7 psi) at 38 L/min (10 GPM) including coil, piping, and quick connects.
6. Coil is protected by perforated sheets, no less than 79% open, on both air inlet and air outlet sides.
7. Coil is UL® Registered (UL207).
2.1.5 Environmental
1. The HTD doesn’t require electrical power connections.
2. The HTD is a completely passive device and has no fans or other active air movement components.
2.2 Optional Components
2.2.1 Flexible Hose Kits
1. Optional Hose Kits are available to provide for connection between the water distribution manifold and the supported HTD
units and consist of a matched pair of hoses with connections.
2. Hoses will be factory assembled; factory pressure tested, constructed of double-walled reinforced Ethylene Propylene Diene
Monomer (EPDM) rubber and have brass ¾" or 1" ISO 7241-1 Series B quick-release couplings on one or both ends to facilitate
rapid installation and reconfiguration. Hoses with a single quick-release coupling will have ¾" MPT connection on opposite end.
3. Hose material is ¾" or 1" ID with minimum wall thickness of 0.14" (0.36 cm), minimum bend radius of 4" (10.2 cm), and
minimum burst pressure of 12.4 MPa (1800 psi).
4. Hose material meets flammability rating of UL® 1581 VW-1 or greater.
5. Hose Kits are pressure tested as an assembly to 1.7 MPa (250 psi).
6. Hose Kits are available with either straight connections or right-angle connections. External right-angle Hose Kits require a
minimum clearance of 2.125" (5.4 cm) between the bottom of the HTD/Enclosure and the floor.
7. One (1) hose kit (with a supply and a return hose) shall be supplied per HTD.
2.2.2 Pre-Mixed Treated Water
1. A secondary loop is filled with particulate-free, DI/RO water with appropriate controls to prevent corrosion, fouling,
scaling, and bacterial growth.
2. Water is treated with azole, molybdate, and isothiazoline.
724-746-5500 | blackbox.com
Page 3
3. Treated water is pre-mixed in the factory without the need to further dilute or enhance it in the field prior to initially filling the
system.
4. Treated water is supplied in containers suitable for easy transportation.
5. Containers are either 5 U.S. gallons or 55 U.S. gallons.
2.2.3 Air Purge Tool
1. Tool consists of two (2) unequal lengths of ¼" refrigerant hose with maximum working pressure of 5.5 MPa (800 psi) and
burst pressure rating of 27.6 MPa (4000 psi).
2. Hoses are 6" (15.2 cm) and 72" (182.9 cm) in length.
3. Hoses are UL® Recognized.
4. One (1) air purge tool is supplied per project site.
3. Service
3.1 General
3.1.1 Installation
1. Install the HTD in accordance with the installation instructions in the user’s manual.
2. Maintain recommended service clearances as outlined in the installation instructions.
3. Installation services will be provided by factory authorized personnel.
4. Each enclosure using an HTD will have all openings blocked wherever possible to ensure that exhaust air is directed through the
HTD. Open U spaces on the front mounting rails should have blanking panels attached. Any cable access holes or other open-
ings in the enclosure roof, base, or side should be blocked off to avoid any leakage of exhaust air.
3.1.2 Startup and Commissioning
1. Start up the unit in accordance with the manufacturer’s startup instructions.
2. Commissioning services will be provided by factory-authorized personnel.
About Black Box
Black Box provides an extensive range of networking and infrastructure products. You’ll find everything from cabinets and racks
and power and surge protection products to media converters and Ethernet switches all supported by free, live 24/7 Tech support
available in 30 seconds or less.
© Copyright 2011. Black Box Corporation. All rights reserved. Black Box® and the Double Diamond logo are registered trademarks, and Cold Front™ is a
trademark, of BB Technologies, Inc. Schrader® is a registered trademark of Schrader-Bridgeport International, Inc. UL® is a registered trademark of Underwriters
Laboratories. Any other third-party trademarks appearing in this manual are acknowledged to be the property of their respective owners.
CFD42UBF24 Planning Guide, version 1
724-746-5500 | blackbox.com
|